Paarl Valleij
About the Project
The Works will be constructed in three phases for a duration of 17 months.
Phase 1A, Phase 1B and Phase 2 consist of:
- Access road tie into Reitz Street
- Roads and stormwater infrastructure
- Stormwater attenuation ponds
- Internal water reticulation
- Bulk water pipeline and associated works
- Internal gravity sewers and connection to existing bulk line
- Sleeves/ducting for electrical, telecommunication and irrigation services
Facts:
- Pipe: Total of 8950m
- Bricks: Total of 5080m2
- Electrical Ducting: Total of 8400m
- Asphalt: Total of 19 770m2
- Kerbs: Total of 7560m